UQ Stormwater Drainage Upgrade and Rectification
St Lucia, Queensland
The project involved the replacement and upgrade of the stormwater infrastructure with the Great Court at University of Queensland in order to rectify problems with the aging infrastructure. The works involved the excavation and replacement of stormwater pipes and pits to the perimeter of the great court. Replacement and upgrade of exposed aggregate garden edging, spoon drains and reinstatement of turfed areas. All works were undertaken whilst the campus remained operational.
PROCUREMENT
- Construct Only
PROJECT SIMILARITIES
- Operational Site
- Scheduling of construction activities to ensure ongoing operation.
- Institutional
- Restrictive Site
Operational Issues
- Operational facility
- Adjacent Heritage Listed Buildings.
- Detailed survey to locate and map existing services.
Project results
- Project Cost – $ 528,000.
- Duration of the Project – 3 weeks.
- Nil LTI’s
Roles
- Project Manager – Gerard Martin
- Site Manager – James McEwan
- Coordination /Administration – Stephen Cannon
UQ School of Psycology Upland Road Redevelopment – Civil works package
St Lucia, Queensland
The project involved converting 10 residential dwellings owned by the University of Queensland into offices for the School of Psychology. The Stage 1 Civil Works scope included – Civil works, Trunk sewer, Water supply, Electrical Conduits, Road works, Fencing, underpinning of houses, and hard/soft landscaping.
PROCUREMENT
- Construct
PROJECT SIMILARITIES
- Scheduling of construction activities to ensure ongoing operation.
- Institutional
- Restrictive Site
Operational Issues
- Civil works
- Underpinning
Project results
- Project Cost – $2,090,000
- Duration of the Project – 10 months project.
- 1 LTI
Roles
- Project Manager – Gerard Martin
- Site Manager – Ron Ryan
- Coordination /Administration – Stephen Cannon
UQ Gatton – Underground Chilled Water Extension and plant room alterations
Gatton, Queensland
The project involved the extension of the existing underground chilled water infrastructure. The existing plant room required structural alterations for the for the installation of larger duckwork and grilles. The works were undertaken whilst the campus remained operational.

PROCUREMENT
- Design & Construct
PROJECT SIMILARITIES
- Operational Site
- Scheduling of construction activities to ensure ongoing operation.
- Institutional
- Restrictive Site
Operational Issues
- Operational facility
- Detailed survey to locate and map existing services.
- Civil Works
Project results
- Project Cost – Final Cost was $ 175,000
- Duration of the Project – 6 weeks.
- Nil LTI’s
Roles
- Project Manager – Gerard Martin
- Site Manager – James McEwan
- Coordination /Administration – Stephen Cannon
UQ Longpocket – Underground Chilled water Extension
Longpocket, Queensland
The project involved the extension of the existing underground chilled water system on campus to serve the Foxtail Building.

PROCUREMENT
- Construct Only
PROJECT SIMILARITIES
- Operational Site
- Scheduling of construction activities to ensure ongoing operation
Operational Issues
- Operational campus
- Installation of high specification pre-insulated HDPE pipework..
- Detailed survey to locate and map existing services.
Project results
- Project Cost –$ 457,000.
- Duration of the Project – 8 weeks.
- Nil LTI’s
Roles
- Project Manager – Gerard Martin
- Site Manager – Ron Ryan
- Coordination /Administration – Stephen Cannon
UQ Longpocket – High Voltage power upgrade
Longpocket, Queensland
The project involved the upgrade of all high voltage power infrastructure across the Longpocket campus. Construction of 4 substations and 2 new switchrooms. Installation of a new ring main involving the installation of conduits via directional boring and open excavation. The works were undertaken whilst the campus remained operational.

PROCUREMENT
- Design & Construct
PROJECT SIMILARITIES
- Operational Site
- Scheduling of construction activities to ensure ongoing operation
Operational Issues
- Detailed survey to locate and map existing services.
- Operational facility
- Installation of conduits using directional drilling technology to ensure protected vegetation and minimise impact to UQ grounds.
Project results
- Project Cost – Final Cost was $4,500,000.
- Duration of the Project – 14 month project.
- Nil LTI’s
Roles
- Project Manager – Gerard Martin
- Site Manager – Ron Ryan
- Coordination /Administration – Stephen Cannon